All Collections
Closeout Help Tutorials
Submittals
How to Track Changes of a Submittal
How to Track Changes of a Submittal
John Chun avatar
Written by John Chun
Updated over a week ago

Step 1: Log in to Closeout.

Step 2: You will be directed to the Projects tab view. Select the project you would like to work in. You can also search for your project using the Search Projects box in the top right-hand corner of the page.

Step 3: Once you are in the desired project, click on the Closeout Submittals option on the left-hand side of the page to access the submittals for your project.

Step 4: You will see all of the submittals for your project.  From here, choose the desired record you’d like to track changes for by hovering over the submittal and clicking the Pencil icon.

Step 5: Select the User Activity tab to view and track the changes for one submittal.

Did this answer your question?